NETL: Oil & Natural Gas Projects: Shale Oil Upgrading Utilizing Ionic Conductive Membranes
Oil & Natural Gas Projects
Exploration and Production Technologies
Shale Oil Upgrading Utilizing Ionic Conductive Membranes Last Reviewed 12/15/2012

DE-FE0000408

Goal
The goals of this project are to develop a process where alkali metal will reduce and scavenge sulfur and nitrogen contained in shale oil in the presence of hydrogen, and also to demonstrate electrolysis of the alkali polysulfide to alkali metal and sulfur.

Performers
Ceramatec, Inc

Collaborators
Companies providing oil samples of at least five (5) gallons include Chevron, Oil Shale Exploration Company (OSEC), and Red Leaf Resources, Inc.

Background
Work performed by Esso/Exxon in the 1970s found sodium to be effective at removing sulfur and heavy metals from bitumen and oil refinery residues and bottoms; in one case, nitrogen level was also reduced. That effort was expanded to examine the effectiveness of sodium and lithium for nitrogen removal. Previous work by Esso/Exxon also proposed using beta aluminum as a membrane for electrolytic regeneration of sodium. This work builds on that concept, but instead uses NaSicon and LiSicon-based membranes to eliminate water reactions.

This project will develop a new technology to upgrade shale oil by utilizing alkali metals to remove nitrogen, sulfur, and other heavy metals, as well as a method to electrolytically regenerate the alkali metals used in the process. The three technical focus areas include:

Impact
Successful development of this technology may provide potential developers of shale oil resources the ability to upgrade oil after retorting, but prior to refining. Currently, only the hydro-treating process is available, which requires considerable hydrogen and may over saturate the oil. The Green River Basin shale oil resource contains over one trillion barrels. This technology may contribute toward developing this important energy resource and reduce our nation?s dependence on foreign oil supplies.

Accomplishments

Current Status (December 2012)
The project has been completed and the process has demonstrated high levels of sulfur and metals removal from a variety of shale oil, heavy oil, or bitumen feedstocks while in most cases increasing API gravity. Nitrogen removal was less successful. Ceramatec is currently communicating with potential industry partners. DOE is awaiting a final technical report.

Project Start: October 1, 2009
Project End: September 30, 2012

DOE Contribution: $3,788,736
Performer Contribution: $947,186

Contact Information:
NETL ? Robert Vagnetti (robert.vagnetti@netl.doe.gov or 304-285-1334)
Ceramatec, Inc ? John Gordon (johng@ceramatec.com or 801-978-2138)
If you are unable to reach the above personnel, please contact the content manager.

Additional Information

Heavy Oil Upgrading Without Hydrogen [PDF-814KB] Paper presented at the 2011 Gas and Oil Expo and Conference, June 7-9, 2011

Progress Reports
Quarterly Progress Report [PDF-607KB] April - June, 2012

Quarterly Progress Report [PDF-1.56MB] January - March, 2012

Quarterly Progress Report [PDF-820KB] October - December, 2011

Quarterly Progress Report [PDF-2.26MB] July - September, 2011

Quarterly Progress Report [PDF-2.05MB] April - June, 2011

Quarterly Progress Report [PDF-2.28MB] January - March, 2011

Quarterly Progress Report [PDF-1.49MB] October - December, 2010

Quarterly Progress Report [PDF-1.17MB] July - September, 2010

Quarterly Progress Report [PDF-364KB] April - June, 2010

Quarterly Progress Report [PDF-223KB] January - March, 2010

Quarterly Progress Report [PDF-358KB] October - December, 2009