Combustion - Fluidized-Bed Combustion
Program Goals
-
To demonstrate the technical and commercial viability of first-generation PFBC technology in U.S. utility applications.
-
To develop and demonstrate the necessary technology base for second- generation PFBC systems.
-
To achieve the following PFBC system performance targets:
PFBC Power System |
First Generation |
Second Generation |
Initial |
Final |
| Net System Efficiency |
40% |
45+% |
50+% |
Target Date |
by 2000 |
by 2010 |
by 2015 |
SO2Emission Relative to NSPS |
1/4 |
1/5 |
1/10 |
NOx Emissions Relative to NSPS |
1/3 |
1/5 |
1/10 |
Air Toxic Emissions Relative to 1990 CAAA |
Meet |
Meet |
Meet |
Capital Cost, $/kW |
1300 |
1100 |
1000 |
Cost of Electricity vs. Conventional PCC Power Plant |
90% |
80% |
75% |
Note:
NSPS -- New Source Performance Standards
CAAA -- Clean Air Act Amendments
|