This course is designed as a familiarization course to increase understanding of the combined cycle process for power generation. During the training, trainees will startup and shutdown the simulated unit in an integrated manner and to be exposed to simple and complex unit malfunctions in the control room and in the field. Course objectives are as follows:

  • Introduce trainees to plant systems and major components and how they dynamically interact
  • Familiarize trainees with the Human Machine Interface (HMI) and plant control and how safe and efficient operation of the unit can be affected by plant problems
  • Provide the trainees with hands-on operating experiences in plant operations using the HMI.
  • Increase trainee understanding of plant equipment and control processes and integrated operations of the plant

Trainees will spend 40% of the time in the classroom and 60% of the time interacting with the Combined Cycle simulator.

Recommended participants:  Engineers, operations personnel, and managers from electric utilities, engineering & construction firms, and equipment vendors with interest in combined cycle plants.

Estimated Length
:  5 days

Simulator:
OTS: Combined Cycle Dynamic Simulator
ITS: IGCC 3D Virtual Immersive Training System


 

Course Schedule:

Combined Cycle Operations

Day 1

Day 2

Day 3

Day 4

Day 5

Classroom

  • Course introduction
  • Simulator OTS overview
  • ITS overview
  • Overview of major plant systems to be used in Simulator Exercises
  • Introduce Combined Cycle startup procedure

 

Classroom

  • Overview of major plant systems to be used in simulator exercises
  • Discuss start of Circulating Water System
  • Discuss Preparation of Fuel System for Startup
  • Discuss Sulfur Recovery Unit (SRU) startup

 

Classroom

  • Discuss Synchronizing GT and loading Turbine Generator
  • Discuss warming HP, IP, and LP Heat Recovery Steam Generator (HRSG) sections

 

Classroom

  • Discuss Steam Turbine (ST) startup and loading
  • Introduce and discuss GT and ST shutdown procedure

 

Classroom

  • Discuss unit shutdown
  • Discuss approaches to maximize efficiencies
  • Discuss common unit malfunctions

 

 

Simulator Exercise

  • Simulator familiarization exercise and screen navigation
  • Field operator Avatar creation and ITS environment familiarization
  • Start Turbine support systems
  • Start Condensate and Feedwater Systems

 

Simulator Exercise

  • Startup Circulating Water System
  • Startup Fuel Systems
  • Draw vacuum in Condenser
  • Start Gas Turbine (GT) and bring to rated speed on natural gas
  • ITS operations to support startup

 

Simulator Exercise

  • ITS Operations to support startup
  • Synchronize GT and load Turbine Generator
  • Warmup HRSG

 

Simulator Exercise

  • ITS operations to support startup
  • Admit steam to ST and bring to rated speed
  • Synchronize and load ST
  • Unit malfunctions – OTS and ITS

 

Simulator Exercise

  • Unit malfunctions
  • Unit shutdown
  • Approaches to maximize efficiency